Sector statutory inspections
Statutory Inspections for Fabrication & Welding
LOLER, PUWER, PSSR and COSHH LEV compliance from one independent inspection body.
Since 2019 all welding fume, mild steel included, is classified as a human carcinogen, and HSE will not accept any indoor welding without engineering control. That makes the extraction and its 14 month test the legal heart of a fab shop, with inspection campaigns still targeting fabricated metals.
SEIS tests the fume LEV and examines the cranes, slings, presses and air in the same programme.
- Independent & impartial
- Competent engineer surveyors
- Reports issued promptly
Fab shop cover
- Fabricators, welders and sheet metal shops
- Structural steel and architectural metalwork
- Fume LEV, lifting and pressure in one programme
- Reports graded for your QSHE system
What needs inspecting in a fabrication shop
The 2019 reclassification changed the shape of compliance here: LEV is required for all indoor welding regardless of duration, general ventilation no longer counts, and the extraction carries a thorough examination and test at least every 14 months. The lifting and pressure estate runs on its usual clocks alongside.
| Equipment | Regime | Statutory position | What you receive |
|---|---|---|---|
| Welding fume LEV (hoods, on-torch, extracted benches) | COSHH | Thorough examination and test at least every 14 months; required for all indoor welding since 2019 | LEV test report to HSG258 |
| Overhead cranes, jibs and runways | LOLER | Thorough examination at least every 12 months | Report of Thorough Examination |
| Chains, slings, shackles and lifting magnets | LOLER | Every 6 months, each item individually identified | Report of Thorough Examination |
| Power presses working cold metal | PUWER | Every 6 months with interlocked, automatic or photo-electric guards; every 12 months with fixed guards or enclosed tools | Written record of thorough examination and test |
| Press brakes and guillotines | PUWER | Inspection at risk-based intervals set by a competent person | Written record of inspection |
| Air receivers serving plasma and shop air | PSSR | Written Scheme where the system exceeds 250 bar litres, report within 28 days | Written Scheme certification and examination report |
| Fork lift trucks and side loaders | LOLER | Every 12 months, with fork arms and attachments every 6 | Report of Thorough Examination |
The press brake runs on risk-based PUWER intervals; only the power press working cold metal carries the fixed statutory cycle. Neither produces a certificate: the output is a written record.
The fume rules that changed everything
HSE safety alert STSU1 followed the international reclassification of all welding fume as a Group 1 carcinogen, with the evidence drawn substantially from mild steel work. The enforcement position since is blunt: no known safe exposure, no indoor welding without LEV, and RPE where extraction alone cannot finish the job.
What an inspector expects at the arc
Engineering control at every indoor welding station, whatever the job length: extracted benches, hoods positioned within capture distance, or on-torch extraction. Where LEV cannot capture everything, supplemented RPE under a proper programme, and RPE outdoors as standard.
The paperwork half is the 14 month thorough examination and test, benchmarked to HSG258, covering capture at each hood rather than just fan function. Fabricated metals businesses have been a standing target of HSE inspection campaigns since the reclassification, so the report gets asked for.
How SEIS covers a fab shop
One programme carries the fume LEV tests, the crane and accessory examinations, the press cycles and the air receiver's Written Scheme, aligned so visits coincide wherever the intervals allow.
Sling registers are itemised piece by piece, because the 6 month accessory cycle is where fab shops most often drift out of date, and press guarding is recorded at each examination since a guarding change moves the statutory interval. Everything lands in the client portal graded for action.
On this page
The fab shop estate: fume, lifting and pressure in the same forty metres
A fabrication and welding shop concentrates three regimes into one workspace. The welding bays answer to COSHH: since HSE strengthened its enforcement position on welding fume in 2019, following the reclassification of mild steel welding fume as a human carcinogen, suitable engineering controls, in practice local exhaust ventilation, are expected for welding indoors, and that LEV answers to the 14 month thorough examination and test. The cranes, jibs and slings that move plate answer to LOLER on the 6 and 12 month tiers. And the compressed air behind the plasma cutter and the tools answers to PSSR wherever receivers cross the threshold.
The sector's compliance centre of gravity is the fume. Welding fume control is where the enforcement attention sits, where the health consequence is gravest and slowest, and where the paperwork is most specific: the thorough examination and test of every extraction system at least every 14 months, by a competent person, against the system's commissioned performance, producing a report that says in numbers whether each hood still protects the welder under it.
The rest of the estate is no less statutory for being quieter, and this guide takes each in turn. But if a fab shop reads one section, it is the next one.
Welding fume is the sector's enforcement centre of gravity: LEV expected for indoor welding, tested every 14 months against commissioning, with lifting and air plant running their own statutory clocks alongside.
Welding fume LEV: what the 14 month test actually judges
The thorough examination and test under COSHH Regulation 9 is not a filter check; it is a performance judgement. The competent person, typically P601 qualified, measures each hood's capture against the benchmarks the system was commissioned to, HSG258 territory: capture velocities at the working position, transport velocities in the ducts, pressures across the fan and filter, and the physical condition of everything from hood lip to discharge. The question is not does the fan run but does this hood still remove the fume before it reaches the welder's breathing zone.
Fab shop LEV fails in characteristic ways the test is designed to catch. Hoods positioned by habit rather than at the fume source, capture collapsing with every extra hand span of distance. On torch extraction underperforming because it was never balanced for the torch actually in use. Systems extended bay by bay as the shop grew, until a main duct sized for four bays starves six. Flexible ducting crushed behind benches. And the universal one: the moveable hood that welding repositioned a hundred times a day and the test finds parked out of the plume.
Between tests, the duty continues: COSHH expects controls maintained in efficient working order, which in practice means the weekly user check, filters and condition on schedule, and defects reported like the safety equipment this is. A failed hood is not an inconvenience; it is a welder breathing what the system was built to remove.
The 14 month test measures each hood against its commissioned performance, and fab shop systems fail by drift, distance and extension; run the weekly checks between tests and treat a starved hood as a stopped job.
Plate handling: the lifting chain from crane to clamp
Moving plate and fabrications is a lifting chain, and every link is statutory. The overhead cranes and jibs sit on the 12 month tier; every chain, sling, shackle, eyebolt, plate clamp and lifting magnet is an accessory on 6 months, and fab shops run more accessories per tonne of crane than almost anyone. Plate clamps and magnets deserve particular attention: they are the links that fail workpieces onto legs, their condition is judgement work an examiner is trained for, and they multiply in drawers exactly like slings.
Fabricated lifting points are the sector's own special case. When the shop welds a lifting lug onto a fabrication, it has manufactured lifting equipment: the design, the weld and the rating are all load bearing decisions, and anything that will be lifted by shop made points repeatedly should be examined like the accessory it is. The habit of grinding a lug off after one lift is not tidiness, it is the correct end of a temporary accessory's life.
The documents are the standard set: Reports of Thorough Examination to Schedule 1 per item, kept until the next report or two years, whichever is later, with the accessory register carrying every clamp and magnet by serial. The two minute retrieval test applies here as everywhere: any examiner, insurer or customer auditor should get from the clamp in the bay to its current report inside two minutes.
Cranes on 12 months, every clamp, magnet, sling and shop made lifting point on the 6 month accessory tier: the fab shop's lifting risk lives in the drawer and on the welded lug, not on the crane rail.
Worked example: the six bay system commissioned for four
A structural steel fabricator runs a shared extraction system commissioned for four welding bays and passing every test for six years. Business grows. A fifth bay is added with a tee into the main duct, then a sixth, each time by a competent duct contractor doing tidy work, and nobody recalculates anything because the system keeps running and the fan keeps humming. The next TExT fails five hoods out of six.
The examiner's table shows the signature of drift by expansion: no hood dead, every hood marginal, capture velocities ten to twenty five per cent under benchmark, transport velocity in the main duct sagging below what welding fume needs. Nothing is broken. Every component works. The system is simply moving the same air it always moved, now shared six ways instead of four, and the report says in numbers what nobody said at either extension: extraction is a calculated system, not a pipe you tee into.
The remedy is engineering, not maintenance: the system rebalanced, the fan and main duct upsized for the real bay count, dampers set and locked, and the whole recommissioned with new benchmarks for the next test to judge against. The fabricator's lasting fix is procedural: no future modification to extraction without a design calculation, the same rule the shop already applies to the steel it sells.
Extraction added to is extraction redesigned: every tee into a main duct changes every hood on it, so no LEV modification ships without the calculation, and the TExT judges the system you actually run, not the one commissioned years ago.
Signs a fab shop's controls have drifted from their commissioning
Fab shop drift is quiet: bays multiply, hoods wander and clamps accumulate; the flags all reduce to controls no longer matching the shop that grew around them.
The fab shop calendar: 14 months is not a year
The sector's calendar carries one interval that defeats annual thinking: the LEV test's 14 months walks through the calendar, landing two months later each cycle, and shops that manage it as the annual test drift out of compliance by arithmetic alone. Anchor it as a hard diary date set from the last test, with the booking made eight weeks ahead so a busy examiner's schedule cannot push you over.
Around it, the fixed points: the 6 month accessory sweep, best run as a single visit where every sling, clamp and magnet is examined together against the register; the 12 month tier for cranes and jibs; and the Written Scheme intervals on the air plant with their 28 day report windows. Fold the PUWER machinery cycle, press brakes, rolls, saws and guarding records, onto the same page at the intervals you have set in writing.
The pairing that saves fab shops money: put the accessory sweep and the crane examinations in the same visit window, and brief the examiner with the service and repair history since last time, because welding repair on a sling or a re roped hoist is exactly the change an examination should know about. And run the two column audit, serviced and examined per asset, quarterly; the compressor on a gold service contract with no scheme examination is this sector's recurring finding too.
Diary the LEV test from its last date, never from the calendar year, sweep the accessory drawer in one 6 month visit, and pair crane and accessory examinations so the shop stops once, not monthly.
The air estate: receivers, plasma packs and the scheme behind the shop
Compressed air is the fab shop's third utility and its quietest statutory duty. The receiver behind the main compressor, and any packaged receiver inside plasma cutters, laser packages or press brake systems, is a pressure system, and above the 250 bar litre threshold PSSR requires a Written Scheme of Examination certified by a competent person before the system runs, examinations to that scheme, and reports within 28 days. Steam, where a shop runs a wash plant or cleaner that raises it, is in scope at any pressure.
The fab shop failure pattern mirrors the sector's LEV drift: air systems grow with the shop. A second compressor is banked in, a receiver is moved, galvanised pipe gets extended bay by bay, and nobody asks whether the scheme still describes the system it certifies. A Written Scheme is a living document tied to the installed system: change the system and the scheme needs reviewing, exactly as extraction needs recalculating.
The examination itself is judgement work on the parts that fail dangerously: shell and welds internally and externally as the scheme directs, safety valves proven at their set pressures, gauges reading true, drains functioning, because a receiver that cannot shed its condensate corrodes from the floor up. Between examinations the shop's duty is the unglamorous one, daily drain down where no auto drain runs, and defects reported like the pressure vessel findings they are.
The receiver, and the ones hidden inside plasma and laser packages, needs a certified scheme, examinations to it and 28 day reports: air systems that grew with the shop need their scheme reviewed, exactly like the ductwork above them.
Running the programme: one body across fume, lifting and air
A fabricator's cleanest compliance arrangement is one independent inspection body covering the LEV testing, the lifting estate and the pressure plant on a single schedule: one relationship that knows the shop, one calendar the office actually runs, and reports in one format the QA system can file against jobs. For a sector that sells into principal contractors and OEM supply chains, that file is commercial: welding fume compliance is now a standard supplier audit line, and the shop that produces its TExT reports, accessory register and crane reports in minutes wins work from the shop that cannot.
Independence has a sharp meaning here: the LEV examiner who also sells ductwork has an interest in findings that generate installation work, and the lifting examiner who services your cranes is marking his own maintenance. An examining body that fixes nothing gives you findings you can spend money on in the right order, and reports every auditor reads at face value.
Then close the loop the sector most often leaves open: act on the reports. A failed hood gets fixed and retested, not filed; a B tier clamp gets its date honoured; an observation trending on a crane rope becomes next quarter's planned work. Compliance in a fab shop is not the absence of findings, it is findings closed faster than the work creates them.
One independent body across LEV, lifting and air gives a fab shop one calendar, audit ready files and findings with no sales interest behind them; the shops that win supplier audits are the ones that close findings, not the ones that never have any.
