Defects Found in Your PUWER Inspection
Plain answers from independent engineer surveyors who write these reports every week.
PUWER handles defects differently from every other regime: no certificate, no fixed statutory cycle, and no report to the authority except for power presses. What you get is a record of inspection and a risk based duty to act on it. Here is what stops, what waits and what you keep.
- Independent & impartial
- Competent engineer surveyors
- Reports issued promptly
Do this first
- Stand down any machine where guarding or interlocks failed
- Walk the finding back to your risk assessment, not the calendar
- Fix a repair date the risk actually supports
- File the record of inspection where an auditor can find it
Which defects stop the machine
A PUWER inspection under Regulation 6 checks that work equipment is safe where its safety depends on how it is installed and can deteriorate: guards, interlocks, emergency stops, controls, hydraulics, structure. There is no statutory defect grading, so the inspector's judgement and your risk assessment do the sorting between what stops now and what is planned in.
The honest dividing line is whether the defect removes a protective measure. A machine whose interlock no longer stops the wheel is running without the safeguard your risk assessment relies on, and using it is the offence, not the defect itself.
| Finding | Severity | What you must do | Who is told |
|---|---|---|---|
| Protective measure defeated: guards, interlocks, stops | Serious | Take the equipment out of use until it is made safe and rechecked | Your own people; there is no authority notification |
| Deterioration that will become dangerous | Time bound | Plan the repair inside the window your risk assessment supports | Your own people, through the record |
| Wear worth watching | Monitor | Note it on the record and check again at the next inspection | Your own people, through the record |
| Power press defects | Statutory | Follow the power press regime, including its examination reports and notification rules | The enforcing authority, for power presses only |
If the equipment also lifts, the lifting function sits under LOLER with its own thorough examination and defect rules; PUWER inspections cover the rest of the machine and the checks between thorough examinations.
Making it safe and proving you did
PUWER compliance after a defect is repair plus record. The regime trusts your judgement on timing and then holds you to the evidence of it.
Repair, recheck, return to service
Repairs follow the finding: a guard remade, an interlock replaced, a stop circuit rewired. Where the defect defeated a protective measure, have a competent person recheck the equipment before it returns to use, because the recheck is what turns a repair into evidence.
Interval discipline matters afterwards. Regulation 6 intervals are risk based, so a machine that produced a serious defect has just told you its interval was too long. Shortening it is the response an inspector expects to see, and the record is where that decision lives.
There is no PUWER certificate, and that matters
Nothing in PUWER creates a certificate, and a provider selling PUWER certification is describing something the regulations do not contain. The compliance evidence is the record of inspection: what was inspected, when, what was found and what was done about it.
Keep each record at least until the next inspection is recorded, and in practice keep the run of them, because the sequence is what demonstrates a working regime to an auditor, an insurer or an HSE inspector. The exception is power presses, which carry their own statutory examination, reports and authority notification, the only place in PUWER where the paperwork resembles LOLER.
What a defect on a PUWER inspection actually changes
A defect found at a PUWER inspection changes your legal position the moment it is written down, and understanding that is the difference between managing the finding and merely filing it. There is no certificate to void: PUWER produces a record of inspection, and a defect entry in that record is a written statement that a safety related part of your work equipment has deteriorated or failed. From that entry onward, you are an employer with documented knowledge.
Regulation 6 exists precisely for this moment: inspection is required where equipment safety depends on installation conditions or where deterioration can lead to danger, and the inspection's whole purpose is to find that deterioration while it is a finding rather than an incident. A defect is therefore the system working. What inspectors judge is not the existence of defects but the traffic between finding and fixing: whether the graded severity produced a proportionate response, on a defensible timescale, evidenced in the record.
Grade every defect explicitly, because an ungraded defect defaults in an investigator's mind to the most serious reading. The practical grades mirror the other statutory regimes: a defect creating immediate danger stops the equipment now; a defect that will become dangerous carries a repair by date; a deterioration worth tracking is recorded with reasons and watched. The grade belongs in the record next to the finding, with the reasoning in one sentence, and our guide to the inspection record shows where each element sits.
The immediate danger finding: stopping equipment without a certificate to revoke
When an inspection finds a defect creating immediate danger, PUWER gives you no examiner's grounding notice to lean on: the stop is your decision, made under your general duty, and made now. That absence of ceremony is exactly why the discipline matters more, because the only thing standing between the finding and the next operator is what you do in the following hour.
Worked example: a conveyor guard defect read as an investigator would
An internal PUWER inspection of a packing line finds the fixed guard over the conveyor's tail drum has a bent corner leaving a gap at the in running nip, wide enough for fingers, on a machine cleaned daily by hand. The inspector grades it immediate danger, and the line stops at 14:10 with the drive isolated and tagged.
Walk the closure as an investigator later would, backwards from the record. The record shows the finding, the grade, the isolation time and the fix: guard removed, corner section replaced rather than bent back, refitted with all fixings, and a functional check that the gap is closed at every point an operator can reach during cleaning. It shows a recheck entry by the inspector the next morning confirming the repair, and the line released at 09:40. It also shows cause: the corner was bent by a pallet strike from the adjacent aisle, so a barrier rail is raised against the guard and the weekly checklist gains a line for guard condition on the aisle side.
Now notice what the investigator cannot find, because it never happened: no gap between finding and isolation while the shift finished, no bent back into shape repair that fails again at the next pallet strike, no verbal only handover that leaves the night shift restarting a tagged machine. The whole file is five entries long and took less effort than the argument it prevents.
The line lost nineteen working hours. The same nip, found by an accident investigation instead of an inspection, costs a finger, a prohibition notice and a prosecution built on the question we started with: when did you know.
Repair, recheck and returning equipment to service on your own authority
Returning defective equipment to service under PUWER carries a trap symmetrical to the stop: with no external examiner mandated, the temptation is to let the repair itself be the authorisation. Resist it. The finding was made by a competent inspection; the closure should be too, and the record should show a named, competent person confirmed the repair before the equipment ran.
Match the repair to the safety function, not to the symptom. A guard defect is closed when the guard again performs its function at every accessible point, which is a test, not a glance. An interlock defect is closed when the interlock demonstrably stops the machine in every mode it protects, including the inching and setting modes where interlock defeats live. A brake, a stop, an emergency cable: each has a functional test, and the record entry that says tested and proven is worth ten that say fitted.
Where the defect had a repair by date rather than an immediate stop, the date is a boundary, not a target. Plan the work inside it, and if the date will be missed, make a positive decision before it passes: either stop the equipment until the repair, or have your competent person record why continued use remains justified and what compensating measures apply. A date that slides past in silence converts a managed defect into documented use of equipment you had declared would become dangerous.
Recheck ruthlessly after third party repairs. The contractor who serviced the press does excellent work and also left the guard fence panel off; the record's recheck entry is where that gets caught, and the inspection regime that assumes competence without verification will eventually document its own blind spot.
The defect handling mistakes that inspectors quote back
Defects found between inspections: the operator's finding is still a finding
The inspection interval is a maximum, not a schedule for noticing. Most equipment defects announce themselves between inspections, to the operator who hears the change, sees the crack or finds the guard loose, and an employer's defect system is judged by what happens to those findings just as much as the formal ones. PUWER's information and training duties exist so operators can recognise danger; the reporting route is what makes that recognition worth anything.
Make the route shorter than the shift. A defect book at the machine, a supervisor empowered to stop the line, a maintenance number that answers: the mechanics matter less than the latency. An operator report that takes three days to reach a decision maker is a system designed to lose the race against the failure it describes.
Treat operator findings with the same grading discipline as inspection findings: graded, recorded, closed with a recheck. The stakes are identical, and the record of an operator report handled well is powerful evidence of a living system rather than an annual ritual. Conversely, the pattern investigators feast on is the defect reported twice by operators, absent from the inspection records, and present in the incident file.
Feed the between inspection findings back into the inspection itself. If operators keep reporting the same guard working loose, the inspection checklist gains that guard, the interval for that machine shortens, and the fixings get engineering attention rather than repeated tightening. Regulation 6 asks for inspection where deterioration can lead to danger; the operators are telling you, in real time, exactly where that is.
When defects change the interval: the loop that proves your system thinks
A defect should never leave your inspection intervals exactly as it found them without somebody deciding so. Regulation 6 intervals are risk based, which cuts both ways: findings of deterioration are evidence the interval is too long for the conditions, and a clean run of inspections is evidence it might responsibly relax. The interval that never moves in either direction is the signature of a system on autopilot.
Work the loop explicitly after any significant defect. Ask what the deterioration rate implies: a guard fixing that works loose in four months makes a six month inspection a coin toss, and the record should show the interval halved with the reason. Ask whether the conditions changed: the machine moved outdoors, the shift pattern doubled, the material got more abrasive. And ask whether the inspection scope caught the defect or the defect found itself: a failure mode the checklist never examined is a checklist finding, not just an equipment one.
Record the decision even when the decision is no change. One line, defect reviewed, isolated cause, interval retained, converts silence into judgement. This is also where the power press exception earns a mention in any defect conversation: presses run on fixed statutory cycles that you cannot relax, and defects there change the maintenance and the in shift checks instead.
Reviewed intervals are also the cheapest credibility you can buy. An inspection record whose intervals visibly respond to findings tells an inspector the system is alive, and that impression colours how every other page of the file is read.
One estate, four regimes: where the PUWER defect sits among the certificates
A defect rarely respects regulatory boundaries, and the estates that handle defects worst are usually the ones that assume the certificate regimes have it covered. A fork lift carries a LOLER report for its lifting function; its brakes, steering, lights and seat interlock are PUWER matters that no thorough examination certifies. A compressor's receiver sits under PSSR; the drive guard and emergency stop are PUWER. The spray booth's airflow is the LEV test's business; the booth's door interlocks are yours.
Route each defect to its own regime and let each regime's machinery run. A brake defect on the truck is graded and closed in the PUWER record even though the truck's LOLER report is current and clean, because that report never looked at the brakes. A guard defect on the compressor does not wait for the next PSSR examination, which would not record it anyway. Cross regime confusion runs the other way too: a chain defect found during a PUWER walk round belongs to the LOLER world, wants the competent person's opinion, and may trigger an examination out of cycle.
The practical tool is a one page split per machine: which regime owns which system, who inspects it, on what cycle, and where the records live. Ten minutes per asset ends the this is covered by the certificate conversation permanently, and it is exactly the map an inspector asks for when a defect on a multi regime machine comes up.
Above all, never read a current certificate as evidence the whole machine is sound. The certificates certify their own scope; the PUWER record is where everything else lives, which is why the machine with four clean certificates can still be carrying the defect that stops it.
Building the defect system from a standing start
If defects on your site currently live in memory, verbal handovers and the fitter's notebook, building the system is a fortnight's work, not a transformation programme, and the defect handling improves the day the first page exists. The sequence matters more than the software.
The whole structure exists to answer four questions quickly: what did you know, when, what did you do, and who confirmed it. Every element above is one of those answers, prepared in advance.